As a result of 3rd party works,the primary ATC (Air Traffic Control) links at a RAF station were disrupted. SNS are contracted to attend within 24 hours, however, within 12 hours the fault had been determined and found with an agreed remedial structure in place. Full rectification including new by-pass fibre were operational within 48 hours.
Project – Repair/re-instate critical fibre links to ATC
Special Resource – SC clearance. Air Side training
Client – Solutions 30/Aquilla
Due to electrical upgrades, new cabling was being installed adjacent the runway. During works, ducts carrying operational fibre were damaged and the fibre links severed. As works to repair the ducts would be necessary, SNS installed a temporary duct system routed around the damaged infrastructure and installed temporary FOSC’s to reinstate the fibre links and have all systems up and running within 48 hours.
Click below to see a few examples of various completed projects.
View Case StudiesTo find out more about how we can help either call on 02381 849774 or click the button below to send us a message.
Get in touch